Templates › CCA Payment Claim
Formal payment claim under the Construction Contracts Act 2002 — the correct legal format for claiming progress payments in NZ.
How to use: Serve this payment claim in writing. The respondent has 20 working days to issue a payment schedule. All fields are editable — click any text to change it.
| Description of Work | Scheduled Amount ($) | % Complete | Claimed ($) |
|---|---|---|---|
| Contract work — [description] | 100,000 | 60% | 60,000 |
| Approved Variation — VO-001 | 5,500 | 100% | 5,500 |